A3 Motorway in Romania, Heading Towards the Opening of the Chiribis-Suplacu de Barcau Section
According to inspections released by the Pro Infrastructura association and reported by HotNews, the 26.35-kilometer section of the Transylvania Motorway between Chiribis and Suplacu de Barcau could open to traffic in December 2026. The project includes the famous viaduct over the water reservoir, which remained incomplete for twelve years following its abandonment by the original construction consortium.

Tools
The 26.35-kilometer motorway section between Chiribis and Suplacu de Barcau, part of the A3 Transylvania Motorway in Romania, could be opened to traffic in early December 2026. The estimate was released by the non-governmental association Pro Infrastructura and relayed by the news outlet HotNews following aerial drone surveys conducted over the entire construction site.
The remaining activities include limited work on road markings, guardrails, expansion joints, and the landscaping of the area near Port-Marca. The contract with general contractor Construcții Erbasu, worth nearly 890 million lei, was signed in November 2023. The works have accumulated a delay of approximately five months compared to the contractual deadline scheduled for the end of July 2026.
The route includes a complex engineering structure consisting of a 1.8-kilometer viaduct with forty-five 40-meter spans, built across a water reservoir. The choice of route dates back to the 2000s to avoid active oil fields and hilly terrain, but the structure had remained unfinished for about twelve years following the termination of the contract with Bechtel in 2013.
In subsequent years, the management of the lot faced several canceled tenders, legal disputes, and contracts terminated due to poor mobilization. The planned opening will connect this segment to the 13.5-kilometer section inaugurated in 2023 between Suplacu de Barcau and Nusfalau.